Highways Department Contract HY/2009/15
Central-Wan Chai Bypass-Tunnel (Causeway Bay Typhoon Shelter Section)
 

Project  
:
 
Contract HY/2009/15 Central - Wan Chai Bypass - Tunnel (Causeway Bay Typhoon Shelter Section)
Year 
: 2013
Client
: Highways Department
Engineer
: Aecom
Main Contractor : China State Construction Company
Scope of Work
:
 
Construction of permanent and temporary diaphragm walls, thickness 1.0m/1.2m/1.5m (mainly 1.5m). The total length of diaphragm wall was 1,866m, and the total excavation area was 85,700m2.