Project Description
Project Description
The Project constructs the new Airport District Police Operational Base, which is ancillary facility for the Third Runway of Hong Kong International Airport. The Police Operational Base is a 7-storey building with a total floor area of approximately 20,000m2.
Scope of Works
Construction of large diameter bored piles as foundation of the police operational base.
– Bored piles: (a) 36 nos., (b) diameter 1.8m to 3m
Owner:
Airport Authority Hong Kong
Engineer:
Aecom Asia Company Limited
General contractor:
Chinney Construction Co., Ltd.
Period of works:
May 2023 to Jun 2024