Project Description

The Project is one of the West Kowloon Cultural District iconic landmark. Xiqu Centre is the first building of the major development for promoting Chinese Opera – Xiqu.

Scope of Works

Construction of foundations and retaining structures, and carrying out open cut excavation works. Foundations include large diameter bored piles with associated pile caps, while retaining structures include sheet pile walls and pipe pile walls with associated curtain grouting.
– Bored piles: (a) 74 nos., (b) diameter 1.5m to 2.5m, (c) average depth 25.5m, (d) max. depth 37m
– Sheet pile walls: (a) 2,756m2, (b) average depth 11.2m
– Pipe piles: (a) 30 nos., (b) diameter 355mm, (c) average depth 10.8m
– Open cut excavation works: (a) 16,520m3

Owner:
West Kowloon Cultural District Authority​

Engineer (Civil & Structural):
Buro Happold International (HK) Ltd.​

Engineer (Geotechnical):
Atkins (China) Ltd.​

General contractor:
Bachy Soletanche Group Limited

Period of works:
Aug. 2013 to Oct. 2014

0
Years in Hong Kong
0M$+
Yearly Turnover
0+
Projects Completed
0+
Employees

You have a project ?

Bachy Soletanche is the Leading and Specialist Geotechnical and Foundation Contractor, contact us without delay.

You have a project ?

Bachy Soletanche is the Leading and Specialist Geotechnical and Foundation Contractor, contact us without delay.