Project Description

The Project constructs overhead viaducts between MTR Lai King station and Kwai Fong station, and between Kwai Fong station and Kwai Hing station. Total length of the viaducts is approx. 1,280m. The works also include construction of elevated stations of Kwai Fong and Kwai Hing.

Scope of Works

Construction of barrettes as foundations for the overhead viaducts between MTR Lai King station and Kwai Fong station, and between Kwai Fong station and Kwai Hing station.
– Barrettes: (a) 43 nos., (b) 3.6m & 6.2m long, (c) 1.2m & 1.5m thick, (d) excavation area 5,014m2

Owner:
Mass Transit Railway Corporation

Engineer:
Freeman Fox & Partners

General contractor:
Dragages et Travaux Publics

Period of works:
May 1979 to Sep. 1979

0
Years in Hong Kong
0M$+
Yearly Turnover
0+
Projects Completed
0+
Employees

Related Techniques

You have a project ?

Bachy Soletanche is the Leading and Specialist Geotechnical and Foundation Contractor, contact us without delay.

You have a project ?

Bachy Soletanche is the Leading and Specialist Geotechnical and Foundation Contractor, contact us without delay.